Project Schedule - Award of Contract: Milestone Date September 2008; Notice to Proceed: Milestone Date October 2008; Mobilize/Start Construction: Milestone Date March 2009; Construct Detour at Fullerton: Milestone Date September 2009; Implement Traffic Detour at Fullerton: Milestone Date October 2009; Open Fairfax County Parkway and EPG Access Road: Milestone Date September 2010; Project Completion: Milestone Date November 2010